INNOVATION | SDG 3, 8, 9, 14
ZEELAND BRIDGE
Rethinking has been applied for this tender. The market was asked how many pillars they could do for 600,000 euros. Purchasing in this way has resulted in significant cost savings. The contractor has achieved a positive side effect of limiting nuisance and lower start-up costs with its solution.
A life cycle has been created for the product used to calculate the environmental impact.
ABOUT THIS PROJECT
Client: Province of Zeeland
Contractor: Gebr. from Kessel
CPV Code: 44114210-7
Period: The contract was awarded on March 30, 2018. Contract duration 4 months.
Activities: Preserving concrete pillars Zeelandbrug
Preservation products:
Elastocolor waterproof